Harvey Jones Outlet

SCOPE:  Install new outfall for treated water effluent line, including concrete placement, rip-rap, bar grate, by-pass pumping, and minor earthwork to connect to existing channel.
PROJECT STATUS: Project Complete
PROJECT DOCUMENTS: Plans
MEETINGS: Pre-Bid (9/13/21), Pre-Con (12/14/21)

 

PROJECT INFORMATION:
CITY: City of Rio Rancho/Village of Corrales
WATERSHED: Montoyas
CONSULTANT: Huitt-Zollars
CONTRACTOR:  CBKN
CONSTRUCTION COST: $279,080.00 +NMGRT
CONSTUCTION START: 1/3/22 – NTP
CONSTUCTION END: Completed

Drone Footage