PROJECT PURPOSE:
Sunset Channel will capture the drainage coming from Sunset Pond (north of Tulip Road) in a pipe and convey it down through the subdivision to the culvert under Lisbon Avenue, and will also serve as a pathway for pedestrian use between Lisbon Ave. and Tulip Rd.
Location:
City of Rio Rancho
Watershed:
Black Arroyo
Estimated Construction Cost:
$757,775.36 +NMGRT
Funding Source:
Start Date:
6/17/24
Estimated Completion Date:
11/11/24
Contractor
CBKN Dirtworks
Project Designer:
SSCAFCA
Project Management:
SSCAFCA
Construction Oversight:
SSCAFCA