Harley’s Pond

Scope:  The purpose of this facility is to attenuate the peak flows from the Tributary A watershed. The pond will discharge to a proposed storm drain in 10th street instead of its historic flow path towards the east.
Project Status: Project Complete
Project Documents: Plans
Meetings: Pre-Bid Meeting (8-31-21), Pre-Con Meeting (10-15-21)

PROJECT INFORMATION:
Location:


City: Rio Rancho
Watershed: Black
Consultant: RESPEC
Contractor:  CBKN
Construction Cost: $1,243,317.50 + NMGRT
Advertise:  9-8-21
Construction Cost: NTP was 10-25-21
Construction End: 3-24-22
Drone Footage