SCOPE: To eliminate aggrading issues and provide erosion protection along the Lower Arroyo Venada Bank Stabilization Project.
PROJECT STATUS: Construction
PROJECT DOCUMENTS: Construction Plans, Lower Arroyo Venada Project Presentation
MEETINGS: Weekly Meetings will be held onsite on Wednesdays
PROJECT INFORMATION:
TOWN: Bernalillo
WATERSHED: Venada
CONSULTANT: SSCAFCA In-House
CONTRACTOR: Pate Construction Company
CONSTRUCTION COST: 2.8 million dollars
ADVERTISE: January 2023
CONSTRUCTION START: NTP was 03-20-2023
CONSTRUCTION END: 200 days